Fire and Fire Surrogate Study -Southeastern Piedmont
|
|
|
Timeline (field season 2000-05)2000April - May Installation of grid points 17 May Beginning of vegetation and fuel sampling 23 May FFS Piedmont site organizational meeting 31 May Start installing pitfall traps; soil sampling begun 19 July Completion of pitfall and pitfall array installation 24 July Pathology work begun 26 July Completion of vegetation and fuel sampling 08 August Bird surveys completed for breeding season 09 August Completion of tree coring and pathology field work 11 August Soil incubation for nutrient availability completed 16 August Bulk density sampling completed 28 August Litter sampling begun 31 August Small mammal traps deployed 01 September Inspection of southern pine beetle (SPB) infestation 02 September SPB cruises to identify possible problems for treatment areas conducted 09 September Pitfall traps opened 13 September Installation of new Rep 1 Thin due to SPB infestations 19 September Buffer cut to control SPB infestation in Rep 2 Burn 28 September Completion of litter sampling 30 September Small mammal traps opened -- trap for 5 days at 2 treatment areas 02 October Vegetation and feul sampling for replacement stand for Rep 1 Thin begun 17 October Processing (drying and weighing) of litter and duff samples completed 26 October Vegetation sampling of Rep 1 Thin New completed; all pre-treatment data collection completed 05-07 November National FFS meeting in Clemson, SC 15 December Small mammal trapping completed 18 December Thinning operations commenced 200105 April Thinning operations completed 10 April Prescribed burning initiated - Rep 1 Burn 11 April Prescribed burn at Rep 3 Burn 12 April Prescribed burn at Rep 2 Burn 01 May Litter and duff pins measured 08 May Post-treatment fuels and vegetation sampling commences 21-23 August Soil collection for microbial diversity conducted 13 September
Field sampling completed for 2001
25 October
Beetle cruise to assess damage for each treatment area 06-08
November
National FFS meeting, Enterprise, OR 23 November-12 Dec Litter and duff desctructive sampling 2002 29 January-12 Feb Southern pine beetle spots GPS’ed for 2000 and 2001 12 February Begin fuel measurements for Thin & Burn treatment areas 25 February Post-thin/pre-burn fuel sampling completed for Thin & Burn sites 07-08 March Rep 1 Thin & Burn prescribed fire 25 March Rep 2 Thin & Burn prescribed fire 28 March Rep 3 Thin & Burn prescribed fire
30
April
Litter and duff pins measured on Thin & Burns
22
May
Begin vegetation and fuel sampling 18
July
Fuels sampling completed for 2002 16-18
July
Beetle cruise for all Clemson treatment areas 30
July
Vegetation data collection completed for 2002 30
July - 14 August
Litter and duff collection for Thin & Burn treatment areas 24-26 September National FFS meeting in Columbus, OH 02 October WS-2000 weather stations and hygrothermographs deployed 03 October MK-III weather stations established 08 October Begin planning for replacement sites because of SPB infestations 22-29 October Landscape Ecosystem Classification (LEC) measured 07 November Data collection for weather stations begins 13 November Replacement site for Rep 1 Control established 14 November Replacement site for Rep 1 Burn established20 November Rep 2 Burn replacement site established 200306 January HOBO weather stations installed 07 January Rep 3 Burn replacement installed05 May Field work begun at replacement sites (Rep 1 Control) 17 June Vegetation fuel work complete for Clemson sites 25 June Fuels data collection completed at Clemson sites 20-23 October National FFS meeting in Sequoia/Kings Canyon, CA 200410 March Prescribed burn conducted at Rep 2 Burn 24 March Rep 1 Burn prescribed burn 19 April Rep 3 Burn prescribed burn 04 May Begin fuel and vegetation sampling on Control sites 04 August Field sampling completed
200510 March Prescribed burn conducted at rep 2 Thin & Burn 06 April Prescribed burn conducted at Rep 1 Thin & Burn 04 May Prescribed burn at Rep 3 Thin & Burn 12 May FFS field work begins on Control sites 08 June Vegetation work completed for all sites except Thin & Burn 15 June Fuels completed for 2005 26 July Begin vegetation sampling at Thin & Burn sites 04 August All FFS field work completed for 2005 17-20 October National FFS meeting, Andalusia, AL |
|